Wantage Leisure Centre

Pellings was appointed by Vale of White Horse District Council to deliver a part Salix-funded decarbonisation project, developing the Council’s successful funding proposal into a deliverable construction project as part of its wider leisure decarbonisation programme.

Built in 1976, the centre comprises a swimming pool, gym, sports hall with four badminton courts, two squash courts, two studios and external courts. The project sought to improve the building’s energy performance through a range of low-carbon technologies and fabric improvements, helping to future-proof the facility while supporting the Council’s long-term sustainability objectives.

The scope of works included the installation of air source heat pumps and solar photovoltaic panels, replacement of the swimming pool roof, upgraded glazing and external wall insulation. Together, these measures formed part of the Council’s wider leisure decarbonisation programme, improving energy efficiency while reducing operational carbon emissions.

Pellings undertook the initial project scoping and coordinated the investigations required to validate the proposed works and develop the procurement strategy. This included preparing the concept design, technical specification and Employer’s Requirements that formed the basis of the tender documentation.

Following the appointment of Ashe Construction, a Pre-Construction Services Agreement (PCSA) phase was undertaken to further develop the detailed design prior to construction. Throughout this stage, Pellings reviewed and coordinated the contractor’s developing proposals, ensuring they remained aligned with the original Salix funding submission, project objectives and Employer’s Requirements.

A range of technical investigations were coordinated to support the project, including structural surveys, heating options appraisals, acoustic surveys, pull testing, elevation surveys, thermal modelling and targeted R&D asbestos surveys. These investigations helped manage project risks, validate the proposed solutions and inform the construction approach.

The project required close coordination between Vale of White Horse District Council, Oxfordshire County Council, Ashe Construction, GLL, specialist consultants and utility providers. A key challenge involved securing the additional electrical capacity needed to support the new low-carbon technologies while carefully programming the works to minimise disruption and maintain the operation of the leisure centre throughout construction.

Pellings remained closely involved throughout the delivery phase, providing project management, contract administration, design review and ongoing technical support to the Council and wider project team, while coordinating stakeholders throughout construction. Through proactive coordination and careful management, Pellings helped deliver this part Salix-funded decarbonisation project, improving building performance, reducing carbon emissions and supporting the Council’s long-term sustainability objectives.