Angel Wharf

Project Overview

Pellings partnered with Haus Block Management and contractor OCL to successfully complete the external cladding remediation at Angel Wharf, a residential development requiring critical safety upgrades. The project aimed to remove and replace the outdated EPS External Wall Insulation (EWI) system and install new aluminium decking and spandrel panels to bring the building up to current safety standards.

Scope of Works

  • Complete removal of the existing EPS External EWI system
  • Installation of a new, compliant insulation system
  • Replacement of aluminium decking
  • Installation of new spandrel panels

Our role as Employer’s Agent and Project Manager required us to oversee all aspects of the project, ensuring that the work was delivered to the highest standard and met stringent safety regulations.

Challenges

  1. Unforeseen Defects: During the removal of the existing façade, hidden defects were uncovered, adding complexity to the project. These defects had to be addressed before continuing with the installation of the new cladding system.
  2. Coordination Across Teams: Navigating the challenges required a high level of collaboration between all stakeholders, including the contractor, OCL, to ensure that any delays were managed effectively and that solutions were implemented without compromising the project timeline.
  3. Maintaining Resident Satisfaction: As with any residential project, keeping the residents informed and minimising disruption was a key priority.

Project Management Approach

Pellings took a proactive approach to project management, working closely with Haus Block Management, OCL, and other third parties to tackle the hidden defects and deliver the project to specification. Our team demonstrated flexibility and resilience in adapting to unforeseen issues, ensuring that these challenges were overcome without compromising on quality or safety.

We also maintained open lines of communication with the residents of Angel Wharf, providing regular updates on progress and ensuring any concerns were addressed swiftly.

Key Results

  • Timely and Successful Completion: Despite the challenges posed by the hidden defects, Pellings managed the project efficiently, achieving practical completion within the agreed timeframe.
  • High-Quality Outcome: The building’s façade now benefits from modern, compliant materials that ensure long-term safety and performance.
  • Collaborative Problem Solving: The success of the project is a testament to the strong collaboration between Pellings, Haus Block Management, and OCL.

This project reinforces our reputation for managing complex remediation works and maintaining strong partnerships with clients and contractors alike.